Engineering Workflows Underground Services

BYDA for Design and Tender: How Long It Takes, When Plans Expire, and How to Lodge One per Site Without Living in the Portal

Every guide to Before You Dig Australia (BYDA, formerly Dial Before You Dig) is written for the person holding the shovel. That is fair, because that is who the scheme protects. But a consulting engineer uses BYDA differently. You want to know what is in the ground before you design, before you quote, and sometimes before the client has decided whether to proceed at all. This guide is for that use.

How long a BYDA enquiry takes

BYDA’s own guidance is that plans typically arrive within minutes, but to allow up to two business days. In practice:

Plan on two business days for a complete set. Lodge on Monday for a Wednesday desk review.

When plans expire

Plans are valid for a limited period from the enquiry date, typically 28 to 30 days depending on the asset owner. After that, you re-lodge. This matters at two points:

  1. Design programs longer than a month. The plans you designed against are stale by the time the contractor lodges their own. Expect minor differences, especially for NBN and telco.
  2. Feasibility that turns into a job later. A plan set from a feasibility study three months ago is background information, not a current record.

PlanInsight lodges the enquiry against the property record and auto-expires the response set after the 30-day window, so nobody in the team quotes from an expired plan without noticing.

What the plans show, and what they do not

Utility plans are the asset owner’s records. They show the approximate alignment of known assets. They do not confirm depth, exact position, or the presence of private and unregistered services. A plan showing a sewer main along the rear boundary tells you there is a sewer main along the rear boundary, somewhere, at some depth.

For a design engineer that is still very useful:

For anything that goes into a drawing at a specific depth or offset, you need a locator and potholing. The plans tell you where to look.

Lodging across many sites

The portal is designed for one enquiry at a time, with a drawn dig area, a project reference and a start date. That is fine for a builder. For a consultancy scoping ten sites a week it is a real time cost, and it means the enquiries are scattered across whoever lodged them.

PlanInsight lodges a BYDA enquiry on your behalf for the property you are looking at, collects the response PDFs as they arrive, and attaches them to the property record. Anyone in the team can open the property and see the plan set alongside the title, boundary, contours and planning overlays. Details on the features page.

Two conditions come with this, and they are important:

A feasibility-stage checklist

When you open a new site, in this order:

  1. Confirm the lot on plan and boundary. Cadastral boundary as DXF covers this.
  2. Pull contours and watercourses in the same DXF. Note fall and drainage direction.
  3. Check planning overlays: flood, bushfire, waterway corridor, easements.
  4. Lodge the BYDA enquiry. Two business days.
  5. Open the survey plan and check for easements and encumbrances.
  6. Read the plan set against the contours. Where is the sewer, where is the stormwater, do they line up with where the site wants to drain?
  7. Write the fee proposal with the constraints named.

Steps 1 to 5 happen on one screen in PlanInsight. Step 6 is where you earn the fee. The consulting engineers page shows the full workflow.